Transformer installation- the best practices from Transformer manufacturers in India

Transformer manufacturers in India, Rajasthan Powergen can solve many problems involved in transformer installation by adopting best practices. The difficulties and safety hazards can be minimised by taking care of certain factors while positioning a transformer. Location has an impact on how the transformer should be set up and  the precautions to be taken in the future.

The Standards
Installing transformers complying with the ANSI, NEMA, and IEEE standards is important in ensuring safe electrical installation and reliable power supply system which is highly important when power quality is an issue.
Transformers can be a challenge in terms of NEC requirements . Correctly designed installation will make sure the conductors and equipment are right sized, protected and deal with the issue of grounding. Incorrect installation can lead to fires from improper protection or conductor sizes and electric shock from inadequate grounding.
Installation Best Practices Some of the particularly important transformer installation best practices are listed below:
1Permanent Grounding:As soon as the transformer is placed permanently the tank should be permanently grounded with a correctly sized and properly installed permanent ground before assembling the unit and carrying out the inspection.
2. Humidity: Nobody should be allowed to access the transformer liquid-filled compartment in case  of excessive humidity or rain. Whenhumidity exceeds 70% , dry air should be continuously pumped into the gas space. Liquid-filled transformers with Nitrogen in the gas space must be purged by pumping dry air for 30 minutes before service personnel can enter the tank. Oxygen concentrations of 19.5% to 23.5% are recommended.
3. Fluid Inspection: When the insulating liquid needs to be drawn out for inspection, always keep make equipment for clean and dry storage of the liquid during inspection and for filtering the liquid before refilling the tank. Make sure that all associated equipment used in the handling of the fluid (hoses, pumps, etc.) are also very clean and dry. When you remove the liquid, its level should not go below the top of windings.
4. Pressure maintenance: Sufficient gas pressure should be maintained to allow a positive pressure of 1 psi to 2 psi all the time, even at low ambient temperature. The pressure-vacuum gauge, will show pressure variations with ambient temperature. Pressure and ambient temperature readings should be recorded .
5. Inspection and filling: Final inspection of the transformer should be done before it is energized, especially if any work has been done inside the tank. All the electrical connections should be checked for tightness. All bushings should be checked for tightness of gaskets. Electrical clearances inside the tank should be checked. One final check should be made to ensure all tools have been removed.
6. Loading: The transformer should be kept under observation during the first few hours of operation under load after applying full voltage . After few days of working, check the oil for oxygen content and dielectric strength. All temperatures and pressures should be checked in the transformer tank during the first week of operation. Except for special designs, transformers may be operated at their rated kVA if the average ambient temperature of the cooling air does not exceed 86'F (30'C) in any 24-hr period, and the altitude does not exceed 3300 ft.
7. Surge arresters: surge arresters must be installed and connected to the transformer bushings/terminals with the shortest possible leads. These arresters may be necessary to protect the equipment from line switching surges and lightning.
8. StructuralConsiderations: Multiple transformers can be mounted on a single pole as long as the weight is evenly distributed, and the total weight is well within the safe limits of the pole.
9. Mounting: Sub-100 kVA single-phase distribution transformers are typically mounted above the secondary mains.
10. Protection: all distribution transformers must have lighting arresters and fused cutouts installed on the primary side.
11. Groundwires: Cover all ground wires with plastic or wood molding to a point 8 feet above the base of the pole.
12. Guying of poles: Correctly installed guy wires can protect the pole line from damage caused by the strain of the line conductors and pole-mounted equipment.

Hence following the best practices, the transformer manufactures in India, Rajasthan Powergen can reduce costs and prevent safety hazards. Keeping in mind the type of transformer to be installed, its purpose and its surroundings during installation is surely a way to minimize hazards.